Background

Eli Lilly retrofitted an old lab with a new design. Commissioning of new equipment and building management system was required.

Objectives

Commission equipment in new flexible lab. Provide all required documentation for maintenance such as receipt verification, installation qualification, operator manuals, maintenance manuals, recommend spares, PMs, and tagging of all assets.

Challenges

Coordination with various construction and equipment suppliers. Gather all relevant information for entry into maintenance system.

Execution

Review lab mechanical drawings and identify all equipment requiring commission. Develop commissioning standard for new flex labs at Eli Lilly. Execute all test cases.

Results

  • Lab commissioned on time
  • Completed on budget
  • New document formats developed and delivered as final package of project